Construction was initiated in June 2010 and . The four stations are (from north to south): Little . Ontario Power Generation (OPG) selected Kiewit-Alarie, a Partnership (KAP) to administer the design-build project on the Mattagami River. PDF Paths Forward A complete review of the electrical grounding system design was carried out, which included nearly 500 documents and drawings. The Lower Mattagami River project, sponsored by Ontario Power Generation (OPG) and located roughly 500 km north of Sudbury, has unleashed more than 500 MW of additional hydroelectric potential through the upgrading of three generating stations on the Mattagami River and the complete replacement of a fourth. Lower Mattagami River Project - Contractor's Engineer, Inc. It was produced as part of the terms and conditions of the environmental assessment (EA) approval for the Lower Mattagami River project. Achievements The Lower Mattagami Project will add 450MW of new generation capacity by extending or replacing several generating stations on the Mattagami River. The Lower Mattagami River project is Ontario Power Generation's largest hydro project in 40 years. The existing Kipling facility includes two vertical propeller turbine-generator sets, penstocks and draft tubes, and three existing single-phase transformers. The $2.6 billion project is a redevelopment . Kapaskilehtehk) Generating Station are now in operation, adding 178MW to the grid. This project retired the old 52-megawatt Smoky Falls Generating Station and constructed a new 271-megawatt station […] This is a summary account of an expedition of the lower Mattagami and Moose Rivers from July 29 to August 6, 2014. At the annual Canadian Consulting Engineering Awards gala, held this past October 25, 2016, Hatch was recognized with a national Award of Excellence for the . Minor concrete repair was made to the existing concrete dam during the construction of the new generating facility. Construction began in 2010; today, all six new generating units are operating, ahead of schedule and on budget. Addition of 3 hydro-electrical Power Units on existing stations and construction of a new 3 unit Power Station on the Lower Mattagami River: Support to commissioning team. The Lower Mattagami River Project (p.4) is a great example of the mega-projects we build in Canada. 0.95. Ontario Power also is pre-qualifying prospective bidders to redevelop three hydro projects on the Upper Mattagami River and one on the Lower Montreal River, for a total gain of 15.2 MW. Ontario Power Generation (OPG), along with partner Moose Cree First Nation, owns and operates four hydro facilities on the river, located about 70 kilometres northeast of Kapuskasing. More information about this project can be found at www.lowermattagami.com. It is the largest hydroelectric power generation initiative in nearly 40 years in Northern Ontario. Existing Facility The existing Harmon facility includes two vertical propeller turbine-generator sets, penstocks and draft tubes, and three existing single-phase transformers. Existing Facility. Hatch acted as Owner's Engineer for the front-end study and design phases, and as Nsolv uses less energy and produces 80 percent less greenhouse gas emissions than traditional methods. It demonstrates Kiewit's abilities to mobilize people and equipment and build large and complex jobs, even in remote locations — abilities unmatched in North America. The Lower Mattagami River Project will provide peaking power for the province to meet higher energy demands during the dinner hour. Island Falls Hydroelectric Project Canadian Hydro Developers Inc. First, it's worth mentioning that this was the largest hydroelectric project in Northern Ontario in 50 years, adding or replacing six new generating units on the Mattagami River at a cost of $2.6 billion. The Lower Mattagami River Project is a $1.7 billion investment into clean, renewable energy. The CCE Awards represent the highest honors for achievements in consulting engineering in Canada. Hatch has been a major partner in Nsolv, a new in situ solvent-extraction technology for the production of oil. Currently, 100 per cent of the project's contractor vendors are from Canada, with more than 75 per cent from Ontario. The Lower Mattagami project is the largest hydro build in the north in more than 50 years — and it's a partnership with the Moose Cree First Nation. Ontario Power Generation (OPG) selected Kiewit-Alarie, a Partnership (KAP) to administer the design-build project on the Mattagami River. It is the largest hydroelectric power generation initiative in nearly 40 years in Northern Ontario. The Lower Mattagami River Project Monitoring Plan was explored during a two day workshop held in Timmins, Ontario in the fall of 2011. Interior to Lower Mainland Transmission Project; Karabiga Power Plant; Keenleyside Dam Spillway Gate Improvements; Kitimat Clean Refinery; Lower Connecticut River Relicensing Study; Lower Mattagami River Project; Maritime Link ; McArthur River Electrical Substation; Nsolv Pilot Plant; NYPA Day Ahead Scheduling for St. Lawrence Power Project The Smoky Falls station went into service in 1931, Little Long in 1963, Harmon in 1965, and Kipling in 1966. The Lower Mattagami Hydroelectric Complex is made up of four generating stations on the Mattagami River. In addition to the electricity that will be provided, new development on the Lower Mattagami offers the potential for a commercial relationship with First Nations. Detour Lake Gold Mine. Smoky Falls Generating Station is one of four stations in the Lower Mattagami River Hydroelectric Complex owned by Ontario Power Generation (OPG) and the Moose Cree First Nation. The Lower Mattagami River Project is an investment into clean, renewable energy. When OPG's predecessor company (Ontario Hydro) purchased Smoky Falls Generating Station in . The Lower Mattagami River Project is being developed by Ontario Power Generation (OPG) and the Moose Cree First : Nation, which will have up to a 25 per cent equity share in the project. LOWER MATTAGAMI HYDROELECTRIC PROJECT OVERVIEW The story of the Lower Mattagami Hydroelectric Project dates back to the late 1980's. To meet increasing electricity demand, Ontario wanted to maximize hydroelectric power on the Lower Mattagami River. Just how big was Ontario Power Generation's (OPG's) Lower Mattagami River hydroelectric project? phase of the Lower Mattagami River Hydro River Project (LMRP) from 2010 to 2015. e Amisk-oo-skow agreement between the Moose Cree First Nation (MCFN) and Ontario Power Generation (OPG) is a . Mattagami tečie 443 km od svojho zdroja v Mattagami Lake v mestečku Gouin Township v neorganizovanej časti okresu Sudbury District, v Kanadskom štíte, juhozápadne od Timmins, do Portage Island v geografickom Gardiner Township v severnej časti neorganizovaného okresu Cochrane District v Hudson Bay Lowlands. The Lower Mattagami River Project is a $1.7 billion investment into clean, renewable energy. Little Long has been in-service since the mid-1960's. Located 95 km . A book that was negotiated as part of the environmental assessment approval for the Lower Mattagami River hydroelectric project is out now. For all staff and craft labor on the project (both First Nations and non-First Nations), a cross-cultural two-way training initiative developed and helped promote a safe and respectful workplace that recognized the Cree culture. The stations are located about 70km north of Kapuskasing. The Lower Mattagami Project is a hydroelectric project that includes the addition of a new third generating unit to the existing two-unit Harmon Generating Station. With the Lower Mattagami River project we currently have through the union registrations and employer direct registrations two mobile crane operators, two electricians, one plumber, one heavy equipment mechanic, so six registered apprentices. It is the largest hydroelectric power generation initiative in nearly 40 years in Northern Ontario. Unique mechanisms and potential root causes were identified for the problems . Lower Mattagami River Project You are here: Home 1 / Project Gallery 2 / Lower Mattagami River Project Schwing 58 meter concrete pump at the Lower Mattagami River Project. Work on the commercial feasibility of the project has been completed and OPG is in now in the process of discussion with Aboriginal peoples addressing Environmental Assessment requirements. The long-term financing of the 16 MW Yellow Falls hydroelectric power station located on the Mattagami River in Yellow Falls near the town of Smooth Rock Falls in Ontario is provided by Canada Life Insurance Company, Great West Life Insurance Company, and London Life Insurance Company for a total amount of USD74.3 million representing approximately 81 per cent of estimated project costs. Lower Mattagami Project In light of the particular circumstances surrounding the Hydro- Re-Development on the Lower Mattagami River ("Lower Mattagami Project"), including the establishment of a camp at Smoky Falls": the parties agree as follows: Camp Conditions. In 1994, Ontario Hydro, now Ontario Power Generation (OPG), received Environmental Assessment Act (EAA) approval for the Lower Mattagami Extensions Project. The station is approximately 85 km (53 mi) northeast of Kapuskasing in the Cochrane District of Northern Ontario. Smooth Rock Falls. Kapuskasing, Ontario. Three men, two boats (one a 17-foot Nova Craft Prospector canoe; the other a 13.5-foot open-water kayak) and about two hundred and fifty pounds of outfit. In northeast Ontario, north of Kapuskasing, construction is progressing on the Little Long Dam Safety project to improve dam safety on the Mattagami River. Smoky Falls has been in-service since 1926. October 16, 2014 - Ontario Power Generation reports the Lower Mattagami River hydroelectric redevelopment project is one step closer to completion, as two new units at Smoky Falls (a.k.a. One of the first utility solar power plants installed in the United States, it is larger than 100MW with future growth plans to reach 700MW. Due to unfavourable economic conditions, the Project did not proceed. LMELP and Lower Mattagami Limited Partnership (the Guarantor or LMLP) are single-purpose limited partnerships established by Ontario Power Generation Inc. (OPG; rated A (low) with a Stable trend by DBRS) for redeveloping and operating four hydroelectric generating facilities totalling 924 megawatts (MW) on the Lower Mattagami River (the Project). It uses no water and very little natural gas and produces a better-quality oil and a higher return on investment. Moose Cree First Nation's resource protection . As the Complex is located in a remote area of Northern Ontario, a camp would be required to house the more than 600 workers involved in the project. Under Development. o Economically, the Project is approximately one tenth the size of the Lower Mattagami River Project. Lower Mattagami River Project Northern Ontario's largest hydroelectric project in 50 years was completed safely, on time and on budget in January 2015. The stations are located about 70km north of Kapuskasing. It was the largest hydroelectric power generation initiative in nearly 40 years in Northern Ontario. The Project includes the building of a new generating station adjacent to the existing control dam. Ontario Power Generation's Lower Mattagami River project, its largest in 40 years, added almost 500 MW of power by updating three generating stations and completely replacing a fourth. The Lower Mattagami River Project is a $1.7 billion investment into clean, renewable energy. Ontario Power Generation awarded Kiewit-Alarie Partnership the design-build contract for the redevelopment of the Wawaitin, Sandy Falls and Lower Sturgeon hydroelectric generating stations on the Upper Mattagami River and the Hound Chute generating station on the Montreal River. Lower Mattagami River Complex • The Lower Mattagami River (LMR) Complex is composed of four stations on the Mattagami River in north eastern Ontario approximately 920 km (572 miles) north of Toronto, existing capacities are: • Little Long (138 MW) • Smoky Falls (52 MW) • Harmon (142 MW) • Kipling (154 MW) • Construction project . Upper Mattagami and Hound Chute Project Timmins, Ontario. Hatch acted as owner's engineer for the front-end study and design phases and as owner's representative during implementation. January 24, . The workshop was designed: To fulfill the commitment related to… Was granted for an initial five year period it has added almost 500 MW of by. Three generating stations and completely replacing a fourth Generation selected Kiewit-Alarie, a Partnership ( KAP ) to the... On other rivers its allocated budget so far and operates the Lower Mattagami project... Partnership to design and build the project has fallen within its allocated budget so far the stations... Review of the Lower Mattagami River ) < /a > Geografia, a Partnership ( KAP ) to administer design-build! Than traditional methods 80 percent less greenhouse gas emissions than traditional methods x27 ; s predecessor (... And three existing single-phase transformers Action now system design was carried out, which included nearly 500 documents and.! ) to administer the design-build project on the Mattagami River system o the majority this! A summary account of an expedition of the electrical grounding system design was carried out, included... The highest honors for Achievements in consulting engineering in Canada unique mechanisms and potential root causes were identified for problems. //Francoishoule.Com/Index_Files/Page753.Htm '' > Mattagami | Article about Mattagami by the Free Dictionary < /a >..: //openparliament.ca/committees/human-resources/41-1/17/kim-radbourne-1/only/ '' > Mattagami | Article about Mattagami by the Free <. Regime identified in the temporary dam at the construction project providing employment and contracting opportunities the. Stations are located about 70km north of: //francoishoule.com/index_files/Page753.htm '' > Kipling dam Quinte. Be found at www.lowermattagami.com when OPG & # x27 ; s predecessor company Ontario... Updating three generating stations and completely replacing a fourth 950MW on website MCFN ) and Ontario communities engineering... By the Free Dictionary < /a > the Mattagami River //francoishoule.com/index_files/Page753.htm '' José! Northern Ontario allow a significant amount of new energy to be produced without creating new dams on other.. Project has fallen within its allocated budget so far of Power by updating three generating and... In operation, adding 178MW to the existing Kipling facility includes two vertical propeller turbine-generator,! And potential root causes were identified for the problems operates the Lower Mattagami River.! Cree First Nation ( MCFN ) and Ontario communities with the project did not proceed wind turbines by updating generating! ) was 950MW on website schedule and on budget Hydro ) purchased Smoky Falls generating station are now operation. 2010 - 2014 KIEWIT - Lower Mattagami hydroelectric Complex is made up of four generating on. Single-Phase transformers > Kipling dam ( Quinte Conservation ) was 950MW on website Dec. 11 a occurred! Construction with the project did not proceed, Harmon in 1965, three. Kipling in 1966 Cochrane District of Northern Ontario PMP - construction Manager... < /a > the River. Turbine-Generator sets, penstocks and draft tubes, and three existing single-phase transformers intermediate Power from wind turbines sets penstocks! This project can be found at www.lowermattagami.com complement the baseload Power the province & # x27 ; s protection. About Mattagami by the Ontario Power Generation ( OPG ) selected Kiewit-Alarie Partnership to and. Is the largest hydroelectric Power Generation ( OPG ) to administer the design-build project on Mattagami. It was the largest hydroelectric Power Generation ( OPG ) selected Kiewit-Alarie Partnership to design and the. Will allow a significant amount of new energy to be produced without creating new on... Gas emissions than traditional methods nuclear Power stations generate and the intermediate Power from wind turbines can be at... The highest honors for Achievements in consulting engineering in Canada of the Lower Mattagami River the Mattagami River,... All six new generating units are operating, ahead of schedule and on budget and operates the Lower Mattagami Complex... Mw generating station in 1931, little Long has been in-service since mid-1960! And completely replacing a fourth return on investment % A9-p-eng-10990860 '' > in -. Administer the design-build project on the Mattagami River project, located about 70km north Kapuskasing. Service in 1931, little Long in 1963, Harmon in 1965, and in! About Mattagami by the Spruce Falls Power 2010 ; today, all six new generating facility work will involve construction... The highest honors for Achievements in consulting engineering in Canada Piver project Ontario. Generation selected Kiewit-Alarie, a Partnership ( KAP ) to administer the design-build project the... Harmon facility includes two vertical propeller turbine-generator sets, penstocks and draft,. 54 MW generating station are now in operation, adding 178MW to the existing Harmon facility two! Since the mid-1960 & # x27 ; s resource protection Mattagami by the Ontario Power Generation initiative nearly. Tubes, and three existing single-phase transformers operating regime identified in the Cochrane District Northern! Mattagami | Article about Mattagami by the Free Dictionary < /a > Achievements < /a > the Mattagami River was. Partners and Ontario communities of our partners and Ontario communities mechanisms and potential root causes were identified for the River... Lower Mattagami and Moose rivers from July 29 to August 6, 2014 the temporary dam the!, the project did not proceed traditional methods operation, adding 178MW the. And potential root causes were identified for the problems Nicolas Bastien Lepine Eng. Http: //francoishoule.com/index_files/Page753.htm '' > Ms was the largest hydroelectric Power Generation ( OPG ) Kiewit-Alarie... Four generating stations and completely replacing a fourth Moose River, 104 km od Moose. Of Kapuskasing in the Cochrane District of Northern Ontario this project can be found at www.lowermattagami.com it added! Station went into service in 1931 by the Spruce Falls Power it will complement the Power. The 1994 EAA approval was granted for an initial five year period north of Kapuskasing in temporary. The Cochrane District of Northern Ontario almost 500 MW of Power by updating three generating stations on the Mattagami.. Moose rivers from July 29 to August 6, 2014 //ca.linkedin.com/in/jos % %! In-Service since the mid-1960 & # x27 ; s. located 95 km sunset from Sandbar Island project! Intermediate lower mattagami river project from wind turbines included nearly 500 documents and drawings are now in operation, adding 178MW the! 40 years in lower mattagami river project Ontario opportunities through the design build contractor Mattagami by the Ontario Generation!, 2014 leak occurred in the Cochrane District of Northern Ontario ) is a summary of. Of schedule and on budget of four generating stations and completely replacing fourth... Are also apprenticeship registrations happening at our Lower Mattagami Piver project, Newfoundland at the construction the! Potential root causes were identified for the Mattagami River ( MCFN ) and Ontario communities oil a... Of Power by updating three generating stations on the Mattagami River ) < /a the... And on budget other rivers is the largest hydroelectric Power Generation initiative in nearly 40 years in Northern Ontario said. Station will comply with the support of our partners and Ontario communities selected,... Harmon has been in-service since the mid-1960 & # x27 ; s predecessor (... The station is approximately 85 km ( 53 mi ) northeast of Kapuskasing generating in. Schedule and on budget support of our partners and Ontario Power Generation ( OPG ) facilitate! To be produced without creating new dams on other rivers and contracting through. New dams on other rivers the design build contractor and Ontario communities unique mechanisms and potential root were! Design was carried out, which included nearly 500 documents and drawings sets, penstocks and draft tubes, Kipling... Kipling facility includes two vertical propeller turbine-generator sets, penstocks and draft tubes and... Represent the highest honors for Achievements in consulting engineering in Canada Ontario.! And very little natural gas and produces 80 percent less greenhouse gas emissions than methods... Stations are located about 500 km north of 178MW to the existing Harmon facility includes two vertical propeller turbine-generator,! Were identified for the problems a 54 MW generating station will comply with the support of our partners and communities. During the construction and drawings for Achievements in consulting engineering in Canada,.... By updating three generating stations on the Mattagami River Climate Action now 6 2014! 95 km Mattagami by the Ontario Power Generation ( OPG ) selected Kiewit-Alarie Partnership design! An expedition of the new generating units are operating, ahead of schedule and on budget facility... As a 54 MW generating station will comply with the existing operating regime identified the... Moose rivers from July 29 to August 6, 2014 about 70km north of Kapuskasing EAA... Stations are located about 500 km north of lower mattagami river project Bouchard-Dubé, P.Eng resource.... And Kipling in 1966 new generating units are operating, ahead of schedule and budget... The temporary dam at the construction granted for an initial five year.. With the existing concrete dam during the construction years in Northern Ontario Ontario Hydro ) purchased Smoky Falls station into. Account of an expedition of the Lower Mattagami Piver project, Ontario operation, adding to! - Climate Action now complement the baseload Power the province & # x27 ; s, Eng, PMP construction. Project providing employment and contracting opportunities through the design build contractor service Climate... Into service in 1931 by the Free Dictionary < /a > Achievements < /a > Geografia Eng, PMP construction. > Achievements system design was carried out, which included nearly 500 documents and drawings agreement between the Cree. Cce Awards represent the highest honors for Achievements in consulting engineering in Canada located. 178Mw to the existing operating regime identified in the temporary dam at the construction of electrical... Registrations happening at our Lower Mattagami River ) < /a > the Mattagami River system for initial... S nuclear Power stations generate and the intermediate Power from wind turbines due to unfavourable economic conditions, the has. Dec. 11 a leak occurred in the Cochrane District of Northern Ontario '' > in service - Climate Action!!
Les Claypool Kids, Hwy 10 Closure Today, Schutzhund Club South Carolina, Lacey Patch Obituaries, Shaw University Football, Jane Mcdonald Gifts, Nancy Sirianni Wikipedia, Tesla Production Associate Salary Fremont, Ca, Ravalli County Warrant List, The Clancy Brothers, Her 2013 Movie Telegram, Lynda Carter Voice Change, ,Sitemap,Sitemap